planjhariap6bqg4
planjhariap6bqg4 planjhariap6bqg4
  • 04-04-2018
  • Mathematics
contestada

8 men complete a work in 40 days. How many days will be taken to complete the samed work if 2 more men join them.

Respuesta :

rpband00
rpband00 rpband00
  • 04-04-2018
Hello there,

There were 8 men who completed a task in 40 days. If you divide 40/8 that is 5 so it took them 5 weeks to complete this task.

Now if you add two more men, that makes it 10 men to complete the work in 50 days. If you divide 50/10 that is 5.
10 days

Hope this helped!

Answer Link

Otras preguntas

What term describes the inheritance of cystic fibrosis? a) polygenic inheritance b) multiple alleles c) incomplete dominance d) recessive genes
A circle has a diameter of 4 meters what is the best approximation of its area use 3.14 to approximate for pi
A dinner plate has a circumference of 106.76 cm. What is the area of the dinner plate? Use = 3.14.
In a Punnet square, a recessive allele is recorded as a A. uppercase letter B. lowercase letter C. number D. symbol
Groups who are on the same side in war
who won the popular vote in the 1876 presidential election
In what direction does an applied force move an object? A.independant to the force B.in the same direction as the force C.perpendicular to the force D.in the op
An email claiming that you have won a lottery might be an example of ________.
What historic change took place during the 1936 presidential election? (ch. 24)?
factor completely 2v^2+11v+5