In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

In a survey, citizens of Joss and Kath counties were asked wheather they voted "yes" or "no" on building a courthouse. The table shows the results. To the neare
Consider the equation 2(5x-4) = ax + b Find a value for a and a value for b so that the equation has only one solution. explain your reasoning. Thank you so mu
y = 20x + 40 y = 30x + 10 x= ? y= ?
Some hippies lived in communes, which were groups in which members shared everything and worked together
What new military technology was used during World War II? Trenches were no longer offered any protection because of these new weapons. List as many new develop
What is the value of x? 2 units 3 units 5 units 8 units
0:00 10:21 - : Decide if the statement is True or False. Arturo likes to watch tv. O True False
I WILL GIVE BRAINLIESTWhich two U.S. leaders have the most influence over foreign policy? Select one:a. The president and the vice-presidentb. The commander-in-
Hi I'm new Who ever explains me the rules and regulations of brainly will get brainliest Everyone who answers will get 25 points
why does East Asia have such a great range of climates?​