15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

write the uses of apron​
A manufacturing company has a pay structure based on job descriptions. As the company moves toward customizing production to meet customers' specific needs, it
Help please What was the importance of the fighting in the Far West?
liz wants to determine which sport students like to play the most at her school.which method will most likely produce a random example.
If you draw a card out of a deck of cards at random, what is the probability that you will draw a 6?
Alex wants to cover his wall with a circular clock that has a diameter of 16 in. How much space will the clock cover on his wall?
I need the answers with work someone please help if not ima fail math
The image shows a model of a nuclear reaction. Which objects could hit other atoms, producing a chain reaction?
Common Core Performance Assessment. The Name Game Pairs of students in Mr. Kuan's class are playing the Name Game. One team member is given a list of attributes
Find the value of x. x = [?]