12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

Please help im confused on both.
a newspaper editor hired a writer for jokes cartoons. the cost for 8 jokes and 6 cartoons is 610usd. the cost of 6 jokes and 8 cartoons is 510usd how much do a
Why a surface that always have a perpendicular is an equipotential
What do ferns and gymnosperms have in common?They are all vascular plants. Reproduction depends on birds, bees, and other animals. They all produce seeds. They
when president woodrow wilson presented the treaty of versailles to the senate
find the horizontal asymptote for y= 5x/x+6 . y = 0 y = −6 none y = 5
There is no about why the shop had to close down
Find the least common multiple of x2 – 2x – 15 and x2 + 2x – 3. (x + 3)(x – 1)(x + 5) (x – 5)(x + 3)(x – 1) (x – 5)(x + 1)(x + 3) (x + 5)(x + 3)(x + 1)
Choose a physical feature discussed in this unit. In a paragraph of 125 words, discuss its effect on the sub-sahara's physical and human geography
PLEASE HELP!! Which revised research question best responds to the information found in the source Original research:question: are student busy schedules creat